1. Station Road, Harmston – 20th March to 16th April with some weekend working but will exclude the Easter weekend (7th – 10th April). 2. Hill Top / Church Lane, Harmston – 17th April to 21st April with an extra day (24th April) allowed for re-lining of the road. This may be incorporated into the 21st April if the resurfacing progresses well.

**As a consequence of recent poor weather the start has been delayed to Wednesday 22nd March**

 

Notification from Lincolnshire County Council:

As you may already be aware carriageway resurfacing works will commence on the 20th March 2023 at the above locations. There are two schemes proposed –

1. Station Road, Harmston – 20th March to 16th April with some weekend working but will exclude the Easter weekend (7th – 10th April). 

2. Hill Top / Church Lane, Harmston – 17th April to 21st April with an extra day (24th April) allowed for re-lining of the road. This may be incorporated into the 21st April if the resurfacing progresses well. 

 

A road closure will be in place for both schemes with local diversions in place. Residents will shortly be receiving a letter advising of these works. Residents within the closure area will have a level of access maintained although delays can be expected due to the nature of these works. I have advised that additional time is allowed for any essential journeys.

I understand that a further scheme is planned to reconstruct the footway (with associated drainage) on the hill section. Once this has been completed a further resurfacing scheme will be programmed to address this section of carriageway.

Published: Friday, 3rd March 2023